New water tanks in Alto Vista in process

Tanki Di Web Na Altovista 1 1

The process for the new reservoir in Alto Vista is proceeding as planned. In March 2024, the concrete foundation was completed. This is followed by the construction of the new water tank’s roof structure and installation of the stiffener ring, a ring which provides proportional support to the structure while increasing the overall strength of the water tank. It will take a few more months for the works to be completed.

Tanki Di Web Na Altovista 3Tanki Di Web Na Altovista 2